The UW Medical Center Northwest renovation and addition now supports up to 2,500 births per year in the completed facility. The project provides a 3,000-sf addition to the facility including a new C-section suite as well as structural updates to the existing Childbirth Center facility (C wing). The project was phased to allow continued operations at the facility during construction.

DCI was the primary structural and civil engineer for the renovation project. During construction of Phase I, the project encountered poorer than expected soil conditions and had to quickly design a new pile-supported slab-on-grade based on information from the project’s geotechnical engineer.

The civil team developed the TESC, grading, and drainage plans for the property.

Project Highlights

  • The structural team designed the north wing’s foundation, shear wall and framing plans and the south wing’s framing and shear wall plans.
  • A new seismic joint between the south wing and the rest of the building allowed the project to stay within budget by eliminating the need to upgrade the south wing (originally built in 1959) to the current building code. This saved the project significantly in both the structural and mechanical sense.
Location: 
Seattle, Washington
Square Feet: 
24,857-SF
Stories: 
1-2
Primary Material: 
Concrete
Steel
Wood
Type: 
Structural
Civil
Sector: 
Healthcare & Science

Social Profiles