The UW Medical Center Northwest renovation and addition now supports up to 2,500 births per year in the completed facility. The project provides a 3,000-sf addition to the facility including a new C-section suite as well as structural updates to the existing Childbirth Center facility (C wing). The project was phased to allow continued operations at the facility during construction.

DCI was the primary structural and civil engineer for the renovation project. During construction of Phase I, the project encountered poorer than expected soil conditions and had to quickly design a new pile-supported slab-on-grade based on information from the project’s geotechnical engineer.

The civil team developed the TESC, grading, and drainage plans for the property.

Location Pin Icon
Location:
Seattle, Washington
Cube Measurments Icon
Square Feet:
24,857
Building Icon
Stories:
1-2
Geometric Shapes Icon
Service:
Structural, Civil
Pie Chart Icon
Industries:
Healthcare, Life Science & Laboratory
Material Shapes Icon
Primary Material:
Concrete, Steel, Wood

Project Highlights

  • The structural team designed the north wing’s foundation, shear wall and framing plans and the south wing’s framing and shear wall plans.
  • A new seismic joint between the south wing and the rest of the building allowed the project to stay within budget by eliminating the need to upgrade the south wing (originally built in 1959) to the current building code. This saved the project significantly in both the structural and mechanical sense.

Latest work

See all
Baumberger Studio Final 2022 0321
project

Timberview VIII

Avenue Bellevue Drone Jan 2023 6 web
project

Avenue Bellevue

Panda Lantern Festival CAEG OK 6
project

Hello Panda Lantern Festival