I’ve got to tell you, the construction of Martin Stadium has been flawless. It really has been. And again, I attribute that and credit a lot of people. What we’re seeing here today is really something very special.”

Bill Moos as quoted in the Spokesman Review

Bringing a World-Class Stadium to the Palouse: Engineering a cutting edge facility for Washington State University

DCI Engineers provided structural engineering for this $65M expansion to the existing football stadium. This project needed to be completed in one off-season, allowing less than 10 months from construction start to the opening football game and features include new club seating and amenity spaces, luxury boxes, and a new press box.

Location Pin Icon
Location:
Pullman, Washington
Geometric Shapes Icon
Service:
Structural
Pie Chart Icon
Industries:
Higher Education, Sports
Material Shapes Icon
Primary Material:
Concrete, Steel

Project Highlights

  • Structural steel was ordered and detailing begun while the architectural design was less than 50% complete. This involved an extraordinary team effort between DCI and the steel fabricator.
  • The new structure was built over an existing plaza and information technology building, and utilized those existing elements for the structural support of the new building.
  • Stadium includes 1,900 premium seats, 21 suites, 44 loge boxes, and 1,300 club seats.

Awards/News

ENR Best Specialty Contracting Project - WSU Martin Stadium Renovation

Latest work

See all
Dameron Architecture Empirefirehouse2
project

Empire Engine House

0120 110 Madison 20140627 100311
project

110 Madison

Baumberger Studio Final 2022 0321
project

Timberview VIII